Defects Liability Period: What It Covers in a Home Build

The defects liability period is the time after handover when the contractor must fix workmanship defects. Learn what it covers, how long it runs, and how retention works.

Defects Liability Period: What It Covers in a Home Build

The defects liability period, known in Indonesia as masa pemeliharaan, is the time after handover when the contractor remains responsible for fixing defects caused by its work. The contract sets how long it lasts, what it covers and how it works, not verbal habit. So it is worth understanding before you sign, not when the first problem appears.

What the defects liability period is

A newly finished house has not yet been tested by daily use. Hairline cracks in plaster, doors that start to stick, or seepage at pipe joints often appear only after a few weeks of occupancy and a wet season. The defects liability period gives the builder time to fix these issues.

Many contracts frame this period with two milestones. Provisional handover (PHO) marks the house as ready to occupy and starts the period. Final handover (FHO) closes it, once every repair obligation has been met. The documents you should receive at the first handover are covered in our article on building handover.

What is usually covered, and what is not

Usually covered

  • Workmanship defects: abnormal plaster or skim-coat cracks, hollow or loose tiles, paint peeling due to poor surface preparation.
  • Leaks in roofs, gutters or wet areas caused by installation.
  • Electrical and plumbing faults caused by installation, such as leaking joints or circuits that differ from the drawings.
  • Frames, doors, windows and hardware that do not work properly.

Usually excluded

  • Damage from misuse, impact, or changes made by others.
  • Normal wear and routine upkeep, such as cleaning gutters or replacing bulbs.
  • Manufactured equipment (pumps, water heaters, air conditioners), which falls under each manufacturer's warranty.
  • Events beyond anyone's control, such as floods or earthquakes, unless the contract states otherwise.

The line between a workmanship defect and damage from use can be thin. That is why the condition of the house at provisional handover should be recorded with photos and a signed handover report. This gives both parties the same reference point.

How long it lasts and how retention works

There is no single standard length for residential projects. The period usually runs for a few months, for example three to six, depending on project size and what the contract says. What matters is that it covers at least one rainy season, because many roof and seepage issues only show up then.

Contracts usually back this up with a retention: a small share of the contract value, commonly around 5%, that the owner holds back. It is released once the period ends and all repairs are complete. Retention is not a penalty. It keeps the repair obligation measurable. How to fit it into your payment schedule is covered in our article on contractor payment terms.

Keep one distinction in mind. The defects liability period deals with everyday workmanship defects. Liability for structural failure is governed separately by construction regulations and the contract, so ask about it as a separate question.

How to report defects so they are resolved

A clear report speeds up the repair. A vague one often leads to long discussions. We suggest these steps:

  1. Record it early. Note the location, the date you found it and what you see. For example: "bedroom 2, west wall, damp patch about 40 cm high, appeared after heavy rain".
  2. Attach photos. Take one close-up and one that shows the room around it.
  3. Send it through the agreed written channel. Written messages or forms are easier to track than phone calls.
  4. Agree a visit and repair date. For active leaks, a temporary fix should come before the permanent repair.
  5. Close it out. Mark each item as complete, ideally with a photo taken after the repair.

Avoid repairing covered items yourself or calling in other tradespeople. It makes the cause harder to trace and may void the contractor's obligation for that item.

What to settle before signing the contract

An orderly defects liability period starts with a clear contract. Before signing, make sure it states:

  • When the period starts and how long it lasts.
  • The retention amount and the conditions for releasing it.
  • Response times after a report, including urgent cases such as leaks.
  • Excluded items, and which manufacturer warranties will be handed over.
  • The final handover procedure and closing documents.

Other clauses worth including are summarised in our article on home construction contract essentials.

How we handle it in design and build

In our new home design and build service, the defects liability period is part of phase 04, Construction & Handover. Before handover, the work is inspected against a quality checklist. Any remaining issues go onto a punch list, a list of minor repairs that are completed and checked one by one.

Once the handover report is signed, the defects liability period runs as set out in the contract. Defect reports go through a documented channel, so you can see which items are closed and which are still open. You can read about the approval points in each phase on our process page.

Frequently asked questions

Are hairline cracks in walls considered defects?

It depends on their pattern and cause. Fine hairline cracks in the skim coat are often linked to material shrinkage and are usually repaired during the period. Cracks that widen, run diagonally or keep coming back need closer investigation.

What if a defect appears after the period has ended?

The routine repair obligation generally ends at final handover. Structural issues are governed separately. That is why a thorough inspection close to the end of the period is worthwhile.

Do repairs during the period cost extra?

Repairs to workmanship defects within the contract scope generally carry no extra charge. Repairs outside that scope, such as damage caused by changes the owner made, are discussed as separate work.